Christian Brook Sewer Separation, Contract 2 - Week of April 29 - May 3
Park Construction Corporation will continue construction activities on the sewer separation project during the week of April 29nd through May 3rd.
Crew 1: Park Construction will be raising catch basins and drain structures to pavement grade on Oak Street between North Street and Salmon Street; and on Salmon Street between Maple Street and Russell Street and on North Street between Hall Street and Dallaire Street. Once blasting has progressed on Oak Street, the crew will begin excavating and installing new drainage piping on Oak Street between North Street and Webster Street.
Crew 2: Capitol Rock with assistance from Park Construction will continue drilling and blasting ledge for the new drainage piping on Oak Street between North Street and Webster Street.
If you have any questions, please reach out to the project team.
Address/Location
Manchester, NH: City
Manchester, NH 03101
Contact
Emergency: 9-1-1