Christian Brook Sewer Separation Contract 1 - Week of May 13th through May 17th
P. Gioioso & Sons and subcontractors will continue working on North St., Dallaire St., Salmon St., and Smyth Road the week of May 13th through May 17th.
The work on Salmon and Smyth will include preparation and installation for sidewalks. Lawns and sprinkler systems that are disturbed during this process will be repaired at a later date. Structures and utilities will be raised within the roads stated in preparation for final pavement.
Police details will be with the crew to direct traffic around the work zones.
If you have any questions, please contact the project team.