Christian Brook Sewer Separation, Contract 2 - Week of May 13 - May 17
Park Construction Corporation will continue construction activities on the sewer separation project during the week of May 13th through May 17th .
Crew 1: Park Construction will be working with the blasting company on Oak Street and installing 48” diameter drain piping and will continue raising catch basins and manhole frames to binder grade on Salmon St and Oak St.
Crew 2: Capitol Rock with assistance from Park Construction will continue drilling and blasting ledge for the new drainage piping on Oak Street between North Street and Webster Street.
Oak Street between North Street and Webster Street will be closed to through traffic with detour signage and police details to direct traffic around the construction zone.
If you have any questions, please reach out to the project team.