Receive alerts from your local agencies
...or text your ZIP CODE to 888777 for mobile alerts

Full Notification

Manchester, NH: City
Friday May 17th, 2024 :: 03:00 p.m. EDT

Advisory

Christian Brook Sewer Separation Contract 1 - Week of May 20th through May 24th

P. Gioioso & Sons and subcontractors will continue working on North St., Dallaire St., Salmon St., and Smyth Road the week of May 20th through May 24th.
 
The work will include raising drainage and utility structures in preparation of final paving. Final paving possibly to begin at the end of the week. Driveways to be repaired after final paving is installed. Sidewalk and pedestrian ramp installation work will continue on Dallaire St., Salmon St. and Smyth Rd. including the loam and seeding of lawns and grass panels.
 
Lawns and sprinkler systems that are disturbed during this process will be repaired at a later date.  
 
Police details will be with the crew to direct traffic around the work zones.
 
If you have any questions, please contact the project team.
 

Address/Location
Manchester, NH: City

Manchester, NH 03101

Contact
Emergency: 9-1-1

Navigate & Discover