Christian Brook Sewer Separation Contract 2 - Week of June 3rd - June 7th
Park Construction Corporation will continue construction activities on the sewer separation project during the week of June 3rd through June 7th .
Crew 1: Park Construction will continue installing 48” diameter drain piping on Oak Street between North Street and Webster Street.
Crew 2: Capitol Rock with assistance from Park Construction will be drilling probes on Belmont Street to establish the extent of ledge to be blasted.
Oak Street between North Street and Webster Street will be closed to through traffic with detour signage and police details to direct traffic around the construction zone.
If you have any questions, please reach out to the project team.