Christian Brook Sewer Separation, Contract 2 - Week of July 15 - July 19
Park Construction Corporation will continue construction activities on the Christian Brook Sewer Separation project during the week of July 15th through July 19th .
Crew 1: Park Construction will continue replacement of the water main on Oak Street, crossing Webster Street. New 18” drain piping will also be installed at this location. Webster Street will be closed to all traffic between Maple Street and Tory Road during this work. Traffic detour signage will be in place to re-route traffic around the construction zone and police details will be on site to direct traffic. The contractor will then continue installation of new 42” and 30” diameter drain piping on Oak Street north of Webster Street. Oak Street will be closed to through traffic between Webster Street and Red Coat Lane with detour signage and police details to direct traffic around the construction zones.
Crew 2: Will continue installation of water services and catch basins on Blodget, Skyview and High Ridge Roads. The Contractor will also install a new water gate valve on Belmont Street between Smyth Road and Sagamore Street in preparation for drain and water improvements on Belmont Street. Streets will be intermittently closed to through traffic with detour signage and police details to direct traffic around the construction zone.
Crew 3: Capitol Rock will continue to drill holes in the ledge at Oak Street and Joe English Lane to assist with breaking out the ledge for the new drain piping on Oak Street.
In support of the Christian Brook Sewer Separation Project, Liberty Utilities and their subcontractor RH White will continue relaying the gas main on Maple Street between North Street and Webster Street. Traffic will be maintained on Maple Street with signage and flaggers to direct traffic.
If you have any questions, please reach out to the project team.