Receive alerts from your local agencies
...or text your ZIP CODE to 888777 for mobile alerts

Full Notification

Manchester, NH: City
Friday July 19th, 2024 :: 02:39 p.m. EDT

Advisory

Christian Brook Sewer Separation, Contract 2 - Week of July 22 - July 26

Park Construction Corporation will continue construction activities on the Christian Brook Sewer Separation project during the week of July 22nd  through July 26th .
 
Crew 1: Park Construction will continue replacement of the water main and installation of the new 18” drain piping on Webster Street. Webster Street will be closed to all traffic between Maple Street and Tory Road during this work. Traffic detour signage will be in place to re-route traffic around the construction zone and police details will be on site to direct traffic. The contractor will also continue installation of new 42” and 30” diameter drain piping on Oak Street north of Webster Street.  Oak Street will be closed to through traffic between Webster Street and Red Coat Lane with detour signage and police details to direct traffic around the construction zones.
 
Crew 2: Will complete installation of the new sewer line on High Ridge Road near Blodget Street. High Ridge Road will be closed between Harrison Street and Blodget Street. Mid-week the crew will start installation of the 24” drain line on Belmont Street between Smyth Road and Sagamore Street. Belmont Street will be closed to through traffic with detour signage and police details to direct traffic around the construction zone.
 
In support of the Christian Brook Sewer Separation Project, Liberty Utilities and their subcontractor RH White will continue relaying the gas main on Maple Street between North Street and Webster Street. Traffic will be maintained on Maple Street with signage and flaggers to direct traffic.
 
If you have any questions, please reach out to the project team.
 

Address/Location
Manchester, NH: City

Manchester, NH 03101

Contact
Emergency: 9-1-1

Navigate & Discover