Receive alerts from your local agencies
...or text your ZIP CODE to 888777 for mobile alerts

Full Notification

Manchester, NH: City
Friday September 6th, 2024 :: 12:37 p.m. EDT

Advisory

Christian Brook Sewer Separation, Contract 2 - Week of September 9 - September 13

Park Construction Corporation will continue construction activities on the Christian Brook Sewer Separation project during the week of September 9th through September 13th .
 
Crew 1: Will be working on Carnegie Street installing drainage piping between Russell Street and Hawthorne Street. Carnegie Street and Hawthorne Street will be closed to through traffic with detour signage and police details on site to direct traffic around the construction zones.
 
Crew 2: Will continue installation of catch basins and piping on Sagamore Street and catch basins and replacing the water main on Joe English Lane. The crew will continue raising structures and paving around the structures in various locations throughout the project areas. Local work zones streets will be temporarily closed around the construction with detour signage and police details to direct traffic around the construction zone.
 
Crew 3: Capitol Rock will continue drilling and blasting ledge for the drainage piping on Carnegie Street in the Linden and Ashland vicinity. Local areas on Carnegie will be closed to through traffic.
 
If you have any questions, please reach out to the project team.
 

Address/Location
Manchester, NH: City

Manchester, NH 03101

Contact
Emergency: 9-1-1

Navigate & Discover