Christian Brook Sewer Separation, Contract 2 - Week of November 25 - November 27
Park Construction Corporation will continue construction activities on the Christian Brook Sewer Separation project during the week of November 25th through November 27th only, there will be no work on November 28th and 29th in honor of the Thanksgiving holiday.
Crew 1: Will continue installation of drain piping on Carnegie Street at Belmont Street and prepare the subgrade for paving on Tory Road between Webster Street and Joe English Lane.
Crew 2: Will be working with Northeast Roads raising catch basins and manhole structures on recently paved streets including Tory Road, Joe English Lane, Red Coat Lane, Sagamore, Birchwood, Blodget, Skyview and High Ridge Roads then pave around the structures.
Crew 3: Northeast Roads will be raising catch Basins and structures on the roads listed above.
Crew 4: Tri-State Curb will continue replacement of granite curbing on Oak Street.
Crew 5: Continental Paving will reclaim the road surface then pave Carnegie Street between Russell Street and Hall Street.
If you have any questions, please reach out to the project team. Happy Holidays !