CMOM Program Contract 5 - Sewer/Drain Rehabilitation & Repair Project: Week of February 3/10/25 - 3/14/25 
Insituform will be working to complete Internal Spot Repairs (ISRs) next week in the existing sewer main as follows:
Monday (3/10) – Taylor Street, from Valley Street to Grove Street; Nashua Street, from Bridge Street to Arlington Street.
Tuesday (3/11) - Webster Street, from Wagner Street to Belmont Street.
Wednesday (3/12) – Shirley Hill Road, from Mast Road to Rockland Ave; Hanover Street, from Kenney Street to Merrimack Street.
Thursday (3/13) – Huntress Street and Milford Street - @ Summerside Ave.
Albanese D&S will be working on Spruce Street, from Beacon Street to Cypress Street, on Thursday (3/13) & Friday (3/14) to excavate test pits & work at end of Chase Ave.