Receive alerts from your local agencies
...or text your ZIP CODE to 888777 for mobile alerts

Full Notification

Manchester, NH: City
Friday April 11th, 2025 :: 03:00 p.m. EDT

Advisory

Christian Brook Sewer Separation, Contract 2 - Week of April 14 - April 18, 2025

Park Construction Corporation will continue construction activities on the Christian Brook Sewer Separation project during the week of April 14th through April 18th.  
 
Crew 1: Will start construction of the new drainage system and water main revisions at the intersection of Webster Street and Hall Street. This work will require closing Webster Street between Dallaire Street and Belmont Street and Hall Street between Carnegie Street and Fiske Street. Detour signage and Manchester Police details will be on site to assist with traffic.
 
Crew 2: Will complete the construction activities on Maple Street near the Webster Street intersection. Maple Street will be closed between North Street and Webster Street and Webster Street will be closed between Oak Street and Ash Street with detour signage and police details to direct traffic.
 
Starting on Monday, Green Mountain, will start rehabilitation of the sewers in the Smyth Road School area on streets including: Sagamore, Birchwood, Blodget, High Ridge and Hillcrest Streets. Notices to affected residents will be provided by the installer as the work progresses.
 
If you have any questions, please reach out to the project team.
 

Address/Location
Manchester, NH: City

Manchester, NH 03101

Contact
Emergency: 9-1-1

Navigate & Discover