Construction Update CMOM Contract 5 - 5/26/25 - 5/30/25 
Albanese D&S will be performing excavation work at the following locations to complete sewer main spot repairs:
Monday (5/26) – Memorial Day Holiday, No Work;
Tuesday (5/27) – Cartier St., from Putnam St. to Sullivan St. (EPR-29);
Wednesday (5/28) – Bodwell St., from West Shore Ave. to Corning Rd. (EPR-07)
Thursday (5/29) – Reed St., from Kelley St. to end of Reed St. (EPR-15);
Friday (5/30) – Charleston Ave., at Rochelle Ave./Carroll St., George St. Intersection (EPR-11)
S/c Insituform will be working at various locations throughout the city, performing sewer main cleaning and CCTV inspections as preliminary work for full-length sewer liners.
Manchester Water Works will install a new water main on Beech St. from Sommerville St. to Shasta St., & Clay St. from Beech St. to Union St. – traffic will be detoured as required.
Looking Ahead, new sewer main installation on McQuesten St., from Second St. to Wentworth St., is scheduled to begin 6/2/25 and will take 1-2 weeks to complete – construction notices will be distributed prior to the start of work.