Christian Brook Sewer Separation 5/27 - 5/30/2025 
Park Construction Corporation will continue construction activities on the Christian Brook Sewer Separation project during the week of May 27th through May 30th.
Crew 1: Will continue construction of the new drainage system on Belmont Street between Gurtner Street and Oak Street. This work will require closing Belmont Street between Gurtner Street and Oak Street and will affect travel routes on connecting streets. Once this work is completed, the crew will start the installation of new drainage piping and structures on Webster Street, starting at the intersection of Belmont Street. Webster Street will be closed to through traffic with detour signage and police details to assist motorists.
Crew 2: Will continue restoration of lawns and sprinkler systems on Carnegie Street, Belmont Street, and the neighborhood bounded by Sagamore Street, Belmont Street, and Skyview. Weather permitting, new drainage piping and structures will be installed on Maple Street at the intersection with Salmon Street. Maple Street will be closed to through traffic with detour signage in place and police details to assist motorists.
Crew 3: Subcontractor, JCB Colby, will place concrete for handicap ramps at various locations on Carnegie and North Streets and on Bruce Road. This activity is weather-dependent.
Address/Location
Manchester, NH: City
Manchester, NH 03101
Contact
Emergency: 9-1-1