Christian Brook Sewer Separation, Contract 2 - Week of June 2 - June 6, 2025

Park Construction Corporation will continue construction activities on the Christian Brook Sewer Separation project during the week of June 2nd through June 6th.
 
Crew 1: Will continue construction of the new drainage system on Belmont Street and on Webster Street between Belmont and Smyth Road. This work will require closing Belmont Street between Carnegie Street and Fiske Street and Webster Street between Hall Street and Smyth Road. Belmont Street and Webster Street will be closed to through traffic with detour signage and police details to assist motorists.
 
Crew 2: Will continue restoration of lawns and irrigation systems on Carnegie Street, Belmont Street and the neighborhood bounded by Sagamore Street , Belmont Street and Skyview. No road closures will be required for this activity.
 
Crew 2 will also be replacing a short section of Water Main on Maple Street at the Salmon Street intersection Maple Street will be closed to through traffic during this time with detour signage and police details available to assist motorists.
 
Crew 3: Subcontractor, Tri-State Curb, will continue installation of granite curbing on North Street, Belmont Street and Carnegie Street at the intersections of these roads. They will also be completing granite curb installations on Sagamore, Birchwood and High Ridge Road. All work is east of Belmont Street. No road closures will be required for this activity.
 
Crew 4:  Subcontractor, Continental Paving, will perform reclamation, grading and paving of the following Streets:

  1. Beech, Ash and Maple Streets: Road closures will be required between North Street and Webster Street. Detours will be in place. Only one street at a time will be closed to all traffic.
  2. Hall Street: Road closure will be required between Fiske Street and Webster Street.
  3. Belmont Street: Road closure will be required between Oak Street and Gurtner Street. Gurtner Street and Rebel Lane crossing Belmont Street will be closed to through traffic.
For all road closures, detour signage and Manchester Police details will be on site to assist motorists.
 
 
If you have any questions, please reach out to the project team.
 