CMOM Program Contract 5 - Sewer/Drain Rehabilitation & Repair Project: Week of June 16 - June 20, 2025 
Albanese D&S will be continuing excavation work on McQuesten St., from Wentworth St. to Second St, to replace the existing sewer main. Work hours are 7am – 3pm. Traffic detours will be setup during those hours, trucks will use Wentworth St. to Thorp St. to access Second St. No parking signs will also be posted as needed. Work is still expected to take another 2 weeks to complete.
S/c Insituform will commence Sewer Main Lining with 1 lining crew at the following locations:
Monday (6/16) – Exchange Ave., from Eve St. to end of Exchange Ave. (Line 26); Eve St., from Whitney Ave. to River Rd. (Line 36); Arizona St., from First Ave. to Gingras Ave. (Line 56).
Tuesday (6/17) – Irwin Drive @ Merrow St., to both ends of Merrow St. (Line 23); Irwin Drive @ Mary Ann E.Back, from Mary Ann Rd. to Michael St. (Line 32).
Wednesday (6/18) – Crestview Circle, at Kearney Circle (Line 44); Irwin Drive, from Union St. to Paule Ave. (Line 18).
Thursday (6/19) – Sommerville St., from Fremont St. to Young St. (Line 4); Porter St., from Hudson St. to Johnson St. (Line 39); Cross Country off Porter St., from Massabesic St. to Hayward St. (Line 8)
Lining work hours are 7am – 5pm. Special notices have been distributed to residences within these lining areas, and 24-hour notices will be distributed as well prior to actual start of lining work advising residents to limit water usage during lining hours and other information.
Thank You.