Receive alerts from your local agencies
...or text your ZIP CODE to 888777 for mobile alerts

Full Notification

Manchester, NH: City
Friday June 13th, 2025 :: 02:52 p.m. EDT

Advisory

Christian Brook Sewer Separation, Contract 2 - Week of June 16 - June 20, 2025

Park Construction Corporation will continue construction activities on the Christian Brook Sewer Separation project during the week of June 16th  through June 20th.
 
Crew 1: Will be replacing the water main on Webster Street from Belmont Street to Pickering Street. This section of Webster Street will be closed to through traffic with detour signage and police details to assist motorists.
 
Crew 2: Will continue restoration of lawns and irrigation systems and performing cleanup of streets and lawns throughout the project area. No road closures will be required for this activity.
 
Tri-State Curb will be installing new curb and resetting curbs on Beech, Ash and Maple Streets. Temporary road closures will be required on these streets with detour signage and police details on site to direct traffic.
 
North East Roads will start raising structures in the area bounded by Belmont Street, Sagamore and Blodget Streets and connecting streets in preparation for final paving. Road Closures will not be required for this activity.
 
During the week of June 23rd, Continental Paving will be placing the top course of asphalt on the following streets: Belmont Street between Smyth Road and Sagamore Street. Sagamore Street from Belmont to Skyview, Blodget Street from Birchwood to Skyview, High Ridge Road from Blodget to the crest of the hill. Birchwood Street will be milled and overlaid between Sagamore Street and Blodget Street.

If you have any questions, please reach out to the project team.
 

Address/Location
Manchester, NH: City

Manchester, NH 03101

Contact
Emergency: 9-1-1

Navigate & Discover